The Challenge - We installed 4 x 4000amp bars in the risers, this was the largest Busbar installation at the time.
EllisCo’s Role - Working with Singers to ensure that this project went smoothly, drawings where developed to help with the installation, making it very simple and easy.
The Outcome - Building powered up on time, with no issues.